6/25 Building Update and Tour
- David Wheeler
- Jun 25
- 1 min read
Things are really moving well in the fellowship building! And we are on schedule for an early July completion. All walls have been primed and painted. Electricians are making significant progress. The ceiling grid is taking shape, the A/C trunk line is almost completed, and the air handlers have been set in place. The retention pond at the rear of our property was enlarged since the addition extended into the previous retention area. New lights are in, and tile has been installed in the restrooms. The restroom cabinets arrived on Monday and are scheduled to be installed by Friday.
This Sunday, after each service, meet David by the auditorium side doors by room 150 for an exclusive tour of the new building.